Satellite imagery analysis by research firm Aterio indicates that IREN's Horizon 4 data center in Texas, built for Microsoft under a $9.7 billion agreement, still lacks backup generators and cooling equipment, raising concerns about year-end delivery. The New Jersey project being developed for Nebius, with approximately 140 megawatts of planned capacity, may slip to 2027.
Microsoft's AI-related capital expenditure last quarter fell roughly $5 billion below expectations, prompting the company to lower its full-year guidance. Its CFO cited delivery delays by third-party cloud service providers as one of the main reasons. A Microsoft spokesperson said its infrastructure strategy remains flexible, while IREN and DataOne declined to comment.
Satellite Imagery Reveals Potential Delays at Microsoft AI Data Center Partners IREN and Nebius
Отказ от ответственности: Контент, представленный на сайте Phemex News, предназначен исключительно для информационных целей.Мы не гарантируем качество, точность и полноту информации, полученной из статей третьих лиц.Содержание этой страницы не является финансовым или инвестиционным советом.Мы настоятельно рекомендуем вам провести собственное исследование и проконсультироваться с квалифицированным финансовым консультантом, прежде чем принимать какие-либо инвестиционные решения.
